How to turn strategy into an implementation plan

An implementation plan translates an approved strategy into initiatives that people can deliver. Each initiative needs a defined result, an accountable sponsor, realistic resources and measures of progress. Management also needs a regular process for resolving issues that affect several teams.
Implementing Strategy
We’ll email you a link to the PDF.
Read the report onlineContents and resources
From an approved strategy to specific initiatives
Board approval establishes the direction of the business. The next task is to agree what each team must do, how the work fits together and which commitments management can make with the people and funding available.
Zenith’s Implementing Strategy guide organises this work around planning, team structure, and process and tools. This article applies that framework to the guide’s example of expanding into new markets with a wider product range. The detailed scenario below is illustrative.
Break the strategy into initiatives with identifiable outputs. In the expansion example, management needs an assessment of the target market, a value proposition suited to those customers and a plan for supplying and supporting the new range. The initiatives can progress in parallel where their dependencies allow.
Some decisions will affect several initiatives. The product team needs the customer requirements established by the market assessment. Operations needs to know the range and service promise before confirming stock, systems and staffing. Put those dependencies into the plan so that each team knows what it needs from the others.
A plan for each initiative
The guide sets out the components of an initiative plan. The useful test is whether the plan gives its sponsor and delivery team enough information to agree the work, commit resources and assess progress. A broad instruction to expand the business leaves those decisions unresolved.
An initiative plan for launch readiness
Illustrative application of the report’s plan components to preparing a business to supply a new market.
- Objectives
- What to agreeThe result the initiative must produce.
- Application to the launchThe business can accept, fulfil and support orders for the agreed product range.
- Sponsor
- What to agreeThe executive accountable for delivery and decisions beyond the team’s authority.
- Application to the launchThe operations director oversees readiness and resolves conflicts with existing operations.
- Workplan
- What to agreeTasks, milestones and dependencies that can be reviewed.
- Application to the launchConfirm supply arrangements, test ordering, train the service team and obtain launch approval.
- Resources
- What to agreeNamed people, their available time and the funding required.
- Application to the launchAllocate operations, IT and service staff, with cover for responsibilities they cannot do alongside the launch.
- Financials and KPIs
- What to agreeExpected benefits, underlying assumptions and measures of progress.
- Application to the launchRecord launch costs and service performance. Track the sales, margin and delivery costs needed to assess the expansion’s contribution.
Framework from Implementing Strategy. Application developed by Zenith for illustration.
People with the authority and time to deliver
The sponsor oversees delivery, contributes expertise and removes obstacles. The initiative lead coordinates the work and maintains the plan. The team needs to know which decisions it can make and which require the sponsor or steering group. In a smaller initiative, one person may perform more than one role.
Resource commitments need to reflect the day job. If the finance manager is required to model the expansion, complete the annual budget and support another initiative at the same time, the plan contains a capacity conflict. Management must phase the work, change priorities or provide additional help before those commitments become missed milestones.
The guide recommends a CEO-led steering group bringing together the key functional sponsors. That gives decisions spanning sales, operations, finance and IT a clear forum. Initiative teams continue to manage the detailed work, with issues brought to the group when they require coordination or authority beyond the team.
Measures of delivery and financial benefit
The plan needs to show both whether the agreed work has been completed and whether the expected benefits are emerging. For the expansion, delivery milestones might include an approved product range, a tested ordering process and a trained service team. The commercial measures cover sales, gross margin and the cost of serving the new customers.
Agree the baseline, the assumptions behind the expected benefit, who will provide the figures and when management will review them. Where several initiatives contribute to the same result, agree how the combined benefit will be assessed so it is counted once.
A launch can finish on schedule while customer take-up falls short. The reporting process should make that visible. Management can then examine the offer, pricing or service model and revise the next stage of investment using the evidence available.
A reporting cycle that leads to decisions
The guide’s reporting cycle starts with a review of the work ahead. Initiative leads update their trackers, and the project management office brings the updates into a consolidated report. That report gives the steering group a view of progress, upcoming commitments and problems requiring its attention.
Keep the update proportionate to the initiative. A useful report identifies what has changed, the effect on delivery or benefits, and the response required. The team should be able to maintain it as part of managing the work. The example below shows how an ordering-system delay could move through that process.
From a delayed milestone to a management decision
Illustrative reporting sequence for the market-expansion example. Select a stage to see what each participant contributes.
The lead explains the delay and its consequences
- Ordering test delayed
- Training affected
- Launch date at risk
- Information required
- Record the unfinished test, why it is late and which training and launch milestones depend on it.
- People involved
- The initiative lead checks the position with IT and the service manager before updating the sponsor.
- Next action
- Set out a recovery proposal, the resources it needs and any decision beyond the team’s authority.
The program view exposes competing commitments
- Initiative updates
- Shared dependencies
- Decision brief
- Information required
- Show the effect on the launch plan and expected benefit, together with any other initiative using the same people.
- People involved
- The project management office consolidates the updates and checks the proposed response with the relevant sponsors.
- Next action
- Give the steering group the options, their delivery and cost implications, and the date by which a decision is needed.
Management agrees the response and assigns the work
- Response agreed
- Owner confirmed
- Plan updated
- Information required
- Compare the available responses, such as reallocating people, phasing the launch or revising its timing.
- People involved
- The CEO-led steering group resolves the competing priorities with the functional sponsors.
- Next action
- Record the decision, accountable owner and revised milestone. Update the forecast and check delivery at the next review.
Illustrative application of the reporting process in Implementing Strategy.
Readiness to begin implementation
Before the program starts, review the initiative plans together. Management should be able to confirm that:
- The initiatives collectively cover the changes required by the strategy, with their dependencies identified.
- Each sponsor and initiative lead understands the result they are accountable for and the decisions they can make.
- People and funding have been allocated against realistic workloads and timing.
- Milestones and benefit measures have agreed baselines, owners and review dates.
- The reporting cycle gives the steering group enough time and information to resolve delivery problems.
The Implementing Strategy report provides the framework, initiative-plan components and reporting examples to use in that discussion. Zenith’s strategy implementation service helps management develop the plans and reporting process with the people responsible for delivery.
Sources and further detail
- Implementing StrategyZenith Strategy Associates
Plan the implementation with your management team
Discuss how to translate your strategy into initiatives, allocate responsibilities and establish a reporting cycle that supports delivery.
Discuss strategy implementation